Cas east garden temporary ice rink exhibit - electrical 30 - 120v 20 amp gfci protected convenience outlets 1 - 480 volt 600 amp 3 phase 4 wire with grounding conductors - to feed a 230 ton chiller unit and connected to cas existing company switch source
This is for a temporary interactive exhibit - 6 week duration providing power to a 15 hp air compressor @ 480v 3phase with a 50 amp fusible disconnect providing 30 - 120 v 20 amp gfci protected circuited cord cap points of connections
Description installation of conduit and conductors for 2 speaker strobe 5 duct detectors 1 heat detector 1 photo electric smoke detector 4 control relay interface with mechanical systems 1 ansul monitoring status
Installing convenience circuits outlets for a photo desk and retail store
This is a museum exhibit hall that will require power/data for audio/visual equipment lighting - communication and signal
General electrical done throughout the facility
This is a temporary power set up for a cafe. it will consist of 3 construction power box feeds rated at 120/208 volts 50 amps. extension cords will be extended from the gfci power outlets located at the construction boxes to the identified appiance loads as identified
This permit is specific to a new exhibit building out - color of life consists of conduit system installation 120 v 20 amp branch circuits for mechnical and lighting equipment communication control cables relocation of exiting life safety speak strobe device
This permit is specific to a new exhibit building out - color of life consists of conduit system installation 120 v 20 amp branch circuits for mechnical and lighting equipment communication control cables relocation of exiting life safety speak strobe device
West garden cafe project - electrical new 480v distribution panel new 112.5 kva transformer new 208/120 distribution panel new shunt trip service disconnect operator new lighting/dimming fixture control panel new appliance exhaust hood heat pump and fan circuits new vfd and motor controls connected to building management system new security cam motion detector and door monitor no fire...
see more
Penguin holding cci phase 3d sabah project 11051d addition two duct detectors addition two 120vac fire damper connections relocate (3) existing fsd from holding room interior to accessible corridor and mechanical room coordinate witness test with sabah/ccsf electrical inspection and ccsf fd
Installation of new 60 ton chiller and assocaited piping pumps and new chilled water coil. new system replaces existing cw coil in ahv-10 service the forum. concrete work includes a housekeeping pad for the chiller. all work per plans
Building Type:
34 - museum
This is a temporary power set up for a cafe. it will consist of 3 construction power box feeds rated at 120/208 volts 50 amps. extension cords will be extended from the gfci power outlets located at the construction boxes to the identified appiance loads as identified
Addition (2) outlets for power acs-008 addition (2) outlets for data acs-008 - acs 001 cas level b1 aquarium holding aquarium control system #08. install new control enclosure for future controls. install 1-1/4 pvc schedule 40 and pvc risers below slab from control enclosure acs-008 to aquarium holding tanks 1-9 and penguin holding 10-11. conduits are for future holding tank monitorin...
see more
Description installation of conduit and conductors for 2 speaker strobe 5 duct detectors 1 heat detector 1 photo electric smoke detector 4 control relay interface with mechanical systems 1 ansul monitoring status
Cas electrical work involves 2 208v circuits to fcu a&b terminations-commission by acco conduit conductors per sabah engineering to fas connection/test by sabah conduit conductors per cas bms connection test by cas building systems
Cas aquarium front of house - life safety support mechanicals systems - power circuits for pumps motors lighting which includes controls and monitoring. this aspect of work will entail demolish of existing electrical circuits. installation of new and reconfiguration of electrical power circuits
Running temporary power 480 volt 3 phase with ground that has a 500 amp trip parallel 350 mcm per phase and one 350 mcm for ground from identified company switch to ice rink chiller unit. total length 120 feet. also two spider box connected units for utility power use
Cas b2a bio lab building out. this will require new electrical circuits and relocation of existing. office lighting and switching relocation emergency lighting installation relocation of fire alarm speaker strobe security card control access
This is a fire alarm safety installation of devices that is specific to alteration of an existing room. annunciator devices will either be installed in new locations and or a rerouting of existing devices