Interior up-fit of 4, 732 sf of existing shell building space. project includes a new demising wall between the tenant suite and rear corridor new doors to the suite and new interior walls ceilings and finishes. the project also includes new plumbing to a sink and refrigerator in the break room and a future icemaker at the bar. fire protection includes rework of the existing sprinkler...
see more
Woodbridge furniture showroom upfit woodbridge furniture showroom upfit will be on the 3rd floor of 200 steele in the space formerly occupied by taylor king on the west end of the building. modifications to existing general construction plumbing fire protection mechanical and electrical upgrades will occur with this upfit
Status:
Application Submitted
Chaddock furniture 1st floor first generation tenant upfit in the 200 steele street showroom. work includes general construction of interior walls ceilings doors windows and finishes as well as associated mep and fire protection upgrades
Status:
Application Submitted
French accents showroom upfit french accents showroom upfit will be in 200 steele street showroom on the 1st floor. upfit work will include general construction plumbing fire protection mechanical and electrical work. space will be used as furniture showroom (mercantile)
Status:
Application Submitted
Kindel furniture upfit project at 200 steele street. upfit is located in the existing building (not within the adjacent addition under construction). project renovates approx. 4, 000 sf of mercantile (furniture showroom) space on level 1. associated permit number for the adjacent addition is cc-16-0923) (site plan for addition/showing existing is sp-16-0051.ra)
The charles harold third floor upfit is located in the 200 steele street showrrom addition currently under construction (permit cc-16-0923). this upfit include drywall partitions in a art gallery type showroom with mechanical electrical and fire protection equipment and systems added ar-18-0023(sprinklers)-cl (added ar-18-0090 fire alarm.ra)
The charles harold first floor upfit is located within the 200 steele street showroom addition. this construction is under the cc-16-0923 permit. the upfit includes drywall partitions in an art gallery type showroom as well as associated fire protection mechanical and electrical systems and equipment (added ar-18-0021 sprinkler.ra) (added ar-18-0090 fire alarm.ra)
Artitalia showroom upfit mercantile upfit for artitalia in 1st floor of 200 steele street showroom including general construction plumbing fire protection mechanical and electrical upgrades associated with upfit
Status:
Application Submitted
(footing/foundation and structural steel only.ra)early release civil and structural package for permitting ahead of 100% shell construction documents. it is anticipated shell permit documents will be submitted in january 2017 trc of site plan still underway. these documents were submitted directly through civil engineer on the project norris clayton with hugh creed & associates projec...
see more
Furniture showroom upfit on the second floor of the new addition at 200 steele street. minor work also within second floor of existing building. scope of work includes new interior partitions and ceiling as well as mechanical plumbing fire protection and electrical trades (added ar-17-0271 sprinkler.ra) added ar-17-0278 fire alarm jc
Furniture showroom upfit on the third floor of the new addition at 200 steele street. project includes interior partitions and ceilings as well as mechanical electrical fire protection and plumbing trades (added ar-18-0009 sprinkler.ra) (added ar-18-0055 fire alarm.ra)
12, 230+ sf upfit for taylor king furniture. include drywall partitions casework mechanical electrical fire protection (added ar-17-0270 sprinkler.ra) (added ar-17-0277 fire alarm.ra)
Highland house upfit includes architectural electrical mechanical and fire protection scope of work. the upfit is wihtin the existing 200 steele street building not the ongoing addition with record no. 16-0923 (addition and existing building shown on trc plan sp-16-0051.ra) (ar-17-0144 fire alarm cl.) (ar-17-0175 fire alarm-amended cl)
The existing third floor includes hancock & moore and taylor king tenants. due to the new addition a new corridor will be cut through these existing spaces to create access from the existing building to the new addition. the egress points for both hancock & moore and taylor king remain as-is. demolition includes partitions mechanical electrical fire protection and plumbing. new work i...
see more
Ar-17-0164 provided approval on corridors for the first and third floor corridors at 200 steele street. based on owner feedback and tenant layout the corridor on the first floor has been relocated. these changes are relfected in the supplemental sheet which replace what was previously approved
These shell permit documents include architectural mechanical plumbing electrical and fire protection for the 200 steele street addition/renovation(bad documents.ra)
Work includes addition of several walls in existing showroom space doors trim electrical and lighting for front is showroom space. _
Construction of corridors on the first and third floors