How long should it take to gut and remodel my kitchen?

An average 12’x12’ kitchen with relocating the plumbing and electrical, updating the insulation in the exterior wall(s), wall texture, paint, relocating new window(s), cabinets, countertops flooring and installing appliances is normally a two week project providing you have all needed materials on site and your specialty contractors on schedule.

Hello , First it depends on how big or small the kitchen is normal 16’x16’ would take around about 3 days to gut the kitchen out and about two weeks to put everything back together for a finish so two weeks being 10 days plus the 3 days to gut the kitchen that’s 13 days add 2 days for clean up total project should last 15 days if its done right.

It really depends on the scale and finishes of the job. a simple remodel with prefab cabinets and counter can be done in 2 weeks, however a custom and high end finishes can make it 6-8 weeks and more. it is important to ask for the effects of the timeline based on your selections.

@prestigeconstruction what aspects of a custom/high-end kitchen remodel make it takes so much longer?

It would really depend on the size of your kitchen, and if you will be installing prefab cabinets, semi- custom cabinets, or only custom cabinets. If using prefab cabinets or semi custom cabinets, it can take anywhere from 3-5 weeks. If using custom cabinets only, it should take about 5-8 weeks.

Depending on the complexity of the kitchen I would estimate it taking anywhere from a month to two months.