Their BuildZoom score of 112 ranks in the top 3% of 128,670 Washington licensed contractors.
Their license was verified as active when we last checked. If you are thinking of hiring Pdx Property Innovations LLC, we recommend double-checking their license status with the license board and using our project planner to get competitive quotes.
San conn: 122 lf of 8 (varies) main (approx. d=08') in (sw beaverton ave). contractor shall building new 4 branch per standard p-262 and core drill tap 8. contractor must verify depth/location and downstream connection point to public system in the field. contact x31026
Single pdf- 608 sf two story addition to relocate main floor bathroom laundry room addition new bathroom (2nd) bedrooms and office mini-split new water service repipe existing fixtures new drywell replace concrete driveway *no work in row* et pt and mt to code *cesspool decommissioned 25-010877-se*
San conn: 250 lf of 8 varies main (approx d=9.4') in ne 19th ave. contractor shall building new 4 branch per standard p-262 and core drill tap 8. contractor must verify depth/location and downstream connection point to public system in the field contact x31026
Contractor to abandon sewer lateral by installing a concrete plug at the interface of the privately maintained pipe and publicly maintained pipe. concrete plugs installed at curb between nw corner row on n polk st & east row on n jersey st from n polk st to existing lateral. 436 lf of 8 pvc main approx. d=7.7 in n jersey st lateral located approx. 15 from us smh ans311 d=6.5 per cop s... see more
Replacing the exterior sewer main from in front of the garage to the end of the driveway via a burst and replacing the clay line under the garage from the two sewer stacks in the basement through the garage to the driveway via a reroute
Install a new sewer main from the house to the city sewer main located at the edge of the driveway via drilling. installing up to 800 of ejection and gravity sewer line with clean outs along the way. installing sewer ejection pump
San conn: 302 lf of 8 varies main approx d=8.5 in n polk ave. contractor to install 8"x6 tee into 8 main and prepare 6 branch to property per standard p-262. contractor to verify all depths and connections in field. contact x31026
San conn: 130 lf of 8 csp combined main approx. d=9.3 in ne multnomah st. contractor shall building new branch per standard p-262 and core drill tap 8"main. contractor must verify depth/location and downstream connection point to public system in the field contact x31026
San conn: 240 lf of 10 vsp main (approx d=12') in n holman st. contractor shall connect to existing branch per standard p-262 (approx l=13 d=unknown') located approx. 155 from us smh aam389. contractor to verify all depths and locations in field. contact x31026
Contractor to replace existing lateral from property line to the edge of the city paved street area per city standard p-262; pbot note location bursting. contractor must verify depth/location and downstream connection point to public system in the field
Building #10 - contractor to replace existing lateral from property line to face of curb per city standard p-262; pbot note location trenching. contractor must verify depth/location and downstream connection point to public system in the field
Existing: 2032 sf 2-story v-b construction single family home with 3 bedrooms and 2 bathrooms proposed: - demolish lean-to shed - demolish existing upstairs deck (85 sf) and replace with new deck (109 sf) - demolish existing main level deck (188 sf) and replace with new deck (300 sf) with new attached accessory 3 seasons room (200 sf) - revised 2nd floor plan: partition existing famil... see more
Contractor to replace existing lateral from property line to face of curb per city standard p-262; pbot note location trenching. contractor must verify depth/location and downstream connection point to public system in the field
Contractor to replace existing lateral from property line to face of curb per city standard p-262; pbot note location trenching. contractor must verify depth/location and downstream connection point to public system in the field
Contractor to replace existing lateral from property line to face of curb per city standard p-262; pbot note location (burst). contractor must verify depth/location and downstream connection point to public system in the field
Contractor to replace existing lateral from property line to face of curb per city standard p-262; pbot note location bursting. contractor must verify depth/location and downstream connection point to public system in the field
Contractor to replace existing lateral from property line to face of curb per city standard p-262; pbot note location bursting. contractor must verify depth/location and downstream connection point to public system in the field
Contractor to replace existing lateral from property line to face of curb per city standard p-262; pbot note location bursting. contractor must verify depth/location and downstream connection point to public system in the field
Contractor to replace existing lateral from property line to face of curb per city standard p-262; pbot note location (burst). contractor must verify depth/location and downstream connection point to public system in the field
Contractor to replace existing lateral from property line to face of curb per city standard p-262; pbot note location bursting. contractor must verify depth/location and downstream connection point to public system in the field